project details

Tonnage:

124

Schedule:

15 Days

Category:

Industrial Building

location:

Washington, Indiana

It was a multistory highrise building which was the extension part of the existing structure. The lack of information made this project a little bit difficult. We were continues to follow up and submit weekly progress reports and log files related to clarifications. RFIs were submitted to the client regularly so that the client was able to answer the pending queries without any delays to keep the Job on track. The project contained 14 stairs to detail and having to coordinate them with main steel was a challenging one.