project details

Tonnage:

51

Schedule:

10 Days

Category:

Commercial Building

location:

San Diego, California

This project was a renovation in the existing building. In renovation structures, the major challenge is the coordination of existing and new structures. Our team sent one-time field verification and it was appreciated by the client. The requirements were structural and 2 stairs in addition. During the project, we faced a lot of information exchange through RFIs and our communication team managed to get a faster response which resulted in the successful completion of the project on time.